Reolink TrackMix LTE Plus Series and Reolink Altas series cameras offer more than just motion recording like other battery-powered cameras—they also support 24/7 continuous recording thanks to their high-capacity battery. This article will guide you through setting up the recording schedule for the Reolink TrackMix LTE Plus and Reolink Altas series cameras on the Reolink software in the following parts:

1. Step-by-Step Instructions

Part 1. Motion Recording

Part 2. Continuous Recording

2. Explanation of Frame Rate

3. Related Articles

1. Step-by-Step Instructions 

The Reolink TrackMix LTE Plus Series and Reolink Altas series cameras support both motion recording and continuous recording. Click the link for the software you're using to access step-by-step setup instructions.

Important Note: The Reolink TrackMix LTE Plus Series does not support use with Reolink NVR.

Part 1. Motion Recording

* Via Reolink App

  • Standalone Camera / Use with Reolink Home Hub

    Step 1. Launch your Reolink App and log in to your camera, then go to Device settings > Camera Recording.
    Via Reolink App  Altas settings page

    Step 2. Enable Camera Recording and then tap Motion Recording Schedule.
    Motion Recording app

    Step 3. Tap Detection Type to select the detection types you want to enable. Tap Save to apply the settings.
    Note: Detection Type is different for some models. Please refer to the actual interface on your device, as it may vary.

    tap detection type  detection type battery-powered cameras

    Step 4. Tap the icon icon to edit the times by swiping the schedule grid. If you want to remove a scheduled period, tap icon icon and then swipe the schedule grids. Blue grids indicate the periods when motion recording is enabled. White grids indicate recording is disabled for the selected time period.

    (Optional) Select All / Erase All: Tap Select All to fill the entire schedule with the selected recording mode. Tap Erase All to remove all scheduled recordings.

    Tap Save to apply the settings.
    paint/earase

  • Use with Reolink NVR

    Step 1. Launch your Reolink App, go to the NVR device settings, and then tap Record to proceed.
    Use with Reolink NVR  NVR record settings

    Step 2. Enable the Record toggle of the device you want to set up, then tap Settings under it. Then tap Motion Recording Schedule to set it up.

    altas NVR recording  altas NVR recording settings

    Step 3. Tap Detection Type to select the detection types you want to enable. Tap Save to apply the settings.
    Note: Detection Type is different for some models. Please refer to the actual interface on your device, as it may vary.
    tap detection type  select detection type  

    Step 4. Tap the icon icon to edit the times by swiping the schedule grid. To remove a scheduled period, tap icon icon and then swipe the schedule grids. Blue grids indicate the periods when motion recording is enabled. White grids indicate recording is disabled for the selected time period.

    (Optional) Select All / Erase All: Tap Select All to fill the entire schedule with the selected recording mode. Tap Erase All to remove all scheduled recordings.

    Tap Save to apply the settings.
    paint/earase

 

* Via Reolink Client

  • Standalone Camera / Use with Reolink Home Hub

    Step 1. Log in to the camera and go to Device Settings > Surveillance > Record.

    Via Reolink Client

    Step 2. Make sure the Enable Record button is turned on, and then click Schedule.
    Enable Record

    Step 3. Click Event Triggered and then select the Detection Types you want the camera to record when motion is detected.
    Note: Detection Type is different for some models. Please refer to the actual interface on your device, as it may vary.
    Detection Type

    Step 4. Select Enable/Disable and click and drag across the timetable to select the recording period (One grid is for an hour). Blue grids indicate periods when recording is enabled. Gray grids indicate periods when recording is disabled. 

    (Optional) Enable All / Disable All: Click Enable All to fill the entire schedule with the selected recording mode. Click Disable All to remove all scheduled recordings.

    Click Save if you finish setting up.
    cam event triggered

  • Use with Reolink NVR

    Step 1. Log in to the camera and go to Device Settings > Surveillance > Record.
    NVR continuous

    Step 2. Make sure the Enable Record button is turned on, and then click Schedule.
    enable the NVR Record

    Step 3. Choose the channel you want to configure and turn on Enable Record to set up. 

    ❶ Select Event Triggered to configure motion alarm recording. Choose one or more Detection Types, such as Person, Vehicle, Animal, or Others.
    ❷ Select Enable/Disable and click and drag across the timetable to select the recording period (One grid is for an hour). Blue grids indicate periods when recording is enabled. Gray grids indicate periods when recording is disabled.
    ❸ (Optional) Click Enable All to fill the entire schedule with the selected continuous recording. This means the camera will record continuously at all times. Alternatively, click Disable All to remove all scheduled recordings and prevent the camera from recording continuously.
    ❹ (Optional) Click Apply to Other Cameras to share the same recording schedule.
    ❺ Click Save if you finish setting up.

    NVR event triggered

 

* Via Reolink NVR Monitor(new UI)

  • Use with Reolink NVR

    Step 1. Click the gear icon to get to the Settings page. Go to Surveillance > Enable Record > Daily Schedule. Click Enable Record to activate the record function.
    Note: 
    1. Depending on the NVR version, the Settings button may be located at either the top or the bottom of the interface.
    2. This Record button controls all cameras connected to your NVR. If disabled (in grey), the cameras will stop recording, regardless of their schedule configurations.

    record daily schedule

    Step 2. Select the camera and enable its record button. Click Alarm and select the detection types you want to enable. Then, click Enable to choose the recording times on the timetable, or select Disable to set periods when you don’t want the camera to record.

    Altas Alarm schedule

    Step 3. (Optional) Tap Apply to Other Cameras to share the same recording schedule.
    Apply to Other Cameras

 

Part 2. Continuous Recording

Note: Smart Battery Mode is designed to optimize energy usage for battery-powered cameras that support continuous recording. It automatically adjusts recording settings based on the battery level to help extend battery life. We will also guide you through the setup process for configuring it.

* Via Reolink App

  • Standalone Use / Use with Reolink Home Hub

    Step 1. Launch your Reolink App and log in to your camera, then go to Device settings > Camera Recording.

    Via Reolink App  Altas settings page

    Step 2. Enable Camera Recording (if it is enabled, simply disregard it) and then tap Continuous  Recording Schedule.
    Continuous  Recording app

    Step 3. Tap the icon icon in the bottom-left corner to swipe over the time slots (One grid is for an hour) you want to schedule. If you want to remove a scheduled period, tap icon icon and then swipe the schedule grids. Blue grids indicate periods when recording is enabled.  White grids indicate recording is disabled for the selected time period.

    (Optional) Select All / Erase All: Tap Select All to fill the entire schedule with the selected recording mode. Tap Erase All to remove all scheduled recordings.

    Click Save if you finish setting up.
    timer schedule on

    Step 4. (Optional) If your camera supports Smart Battery Mode, you can go back to the Camera Recordings page and tap Smart Battery Mode to set it up.

    By default, the Low Frame Rate range is set to 10%–80%, and it is recommended to leave this setting unchanged. If you notice excessive battery consumption, you can widen the range to reduce power usage.

    smart battery mode on  set up smart battery mode

    For the Reolink Altas Series cameras, you can configure the frame rate (fps). The default frame rate is set to 3 fps, but you can also select from options of 1 or 5 fps. 
    Note: Frame rate cannot be adjusted for the Reolink TrackMix LTE Plus.

    altas frame rate

  • Use with Reolink NVR

    Applies to: RLN8-410 (N7MB01), RLN16-410 (N6MB01), RLN36, NVS36 and RLN12W with latest firmware v3.5.1 or later.

    Step 1. Launch your Reolink App, go to the NVR device settings, and then tap Record to proceed.

    Use with Reolink NVR  NVR record settings

    Step 2. Enable the Record toggle of the device you want to set up, then tap Settings under it. Then tap Continuous Recording Schedule to set it up.

    altas NVR recordingaltas NVR recording settings

    Step 3. Tap the icon icon to edit the times by swiping the schedule grid. If you want to remove a scheduled period, tap icon icon and then swipe the schedule grids. Blue grids indicate the periods when motion recording is enabled. White grids indicate recording is disabled for the selected time period.

    (Optional) Select All / Erase All: Tap Select All to fill the entire schedule with the selected recording mode. Tap Erase All to remove all scheduled recordings.

    Tap Save to apply the settings.

    altas timer schedule
     

* Via Reolink Client

  • Standalone Use / Use with Reolink Home Hub

    Step 1. Log in to the camera and go to Device Settings > Surveillance > Record.
    Via Reolink Client

    Step 2. Make sure the Enable Record button is turned on, and then click Schedule.
    Enable Record

    Step 3. Click Continuous, then select Enable/Disable and click and drag across the timetable to select the recording period (One grid is for an hour). Blue grids indicate periods when recording is enabled. Gray grids indicate periods when recording is disabled.

    (Optional) Select All / Erase All: Tap Select All to fill the entire schedule with the selected recording mode. Tap Erase All to remove all scheduled recordings.

    Click Save if you finish setting up.
    Continuous

    Step 4. (Optional) Smart Battery Mode: When Smart Battery Mode is enabled, the camera automatically adjusts Continuous Recording based on the current battery level to extend battery life. Smart Battery Mode divides the battery level into three ranges. As the battery level decreases, the camera automatically switches Continuous Recording from Full Frame Rate to Low Frame Rate, and finally Disable. You can adjust the battery level thresholds based on your recording and battery life requirements.

  • Use with Reolink NVR

    Step 1. Log in to the camera and go to Device Settings > Surveillance > Record.
    NVR continuous

    Step 2. Make sure the Enable Record button is turned on, and then click Schedule.
    enable the NVR Record

    Step 3. Click Continuous, then select Enable/Disable and click and drag across the timetable to select the recording period (One grid is for an hour). Blue grids indicate periods when recording is enabled. Gray grids indicate periods when recording is disabled.

    (Optional) Select All / Erase All: Tap Select All to fill the entire schedule with the selected recording mode. Tap Erase All to remove all scheduled recordings.

    Click Save if you finish setting up.
    NVR continuous

 

* Via Reolink NVR (new UI)

  • Use with Reolink NVR

    Applies to: RLN4E, NVS4E, RLN8-410 (hardware version H3MB18/N2MB02/N3MB01/N7MB01/NVR_NNT3NA78P), RLN16-410 (hardware version H3MB18/N6MB01/NVR_NNT4NA716P), RLN36, RLN12W, NVS8, NVS12W, NVS16, NVS36, RP-PN8, RP-PN16, RP-N64.

    Step 1. Click the gear icon to get to the Settings page. Go to Surveillance > Enable Record > Daily Schedule. Click Enable Record to activate the record function.
    Note: 
    1. Depending on the NVR version, the Settings button may be located at either the top or the bottom of the interface.
    2. This Record button controls all cameras connected to your NVR. If disabled (in grey), the cameras will stop recording, regardless of their schedule configurations.

    record daily schedule

    Step 2. Select the camera and enable its record button. Click Timer, then click Enable to choose the recording times on the timetable, or select Disable to set periods when you don’t want the camera to record.
    Altas Timer schedule

    Step 3. (Optional) Tap Apply to Other Cameras to share the same recording schedule.
    Apply to Other Cameras

2. Explanation of Frame Rate

Additional Notes for Reolink Altas Series Cameras:

The Altas series cameras support three frame rate settings: Stream FPS, Smart Battery Mode FPS, and Pre-recording FPS.

Altas stream fps

altas smart battery mode frame rate

pre-record frame rate

  • When both pre-recording and smart battery mode are off, the frame rate matches the stream mode setting.
  • When smart battery mode is enabled, the frame rate depends on the battery status:
    • In low frame rate situations, it matches the smart battery mode setting.
    • In full frame rate situations, it matches the stream mode setting.
  • When pre-recording is enabled, in low frame rate situations, the frame rate will prioritize pre-recording settings.
  • If the camera is in live view or if Motion Detection (MD) or PIR is triggered, the frame rate reverts to the stream mode setting regardless of the current situation.

3. Related Articles

Efficient Continuous Recording: Smart Battery Mode Explained.

How Long Does the Battery Last for Reolink TrackMix LTE Plus and Reolink Altas Series

If you have any questions, click “Submit a request” below to contact the Reolink Support Team.